Inside the $600 Billion Structure

The headline number is $250 billion, but that only covers one half of what Nvidia is reportedly discussing. The guarantee under negotiation would backstop the construction debt and lease payments for OpenAI's 10-gigawatt Ohio campus - the Nvidia chips that fill the buildings are explicitly carved out and covered by a second, separate financing conversation worth up to $350 billion [1]. Add the two together and Nvidia's potential exposure runs toward $600 billion [2]. The site itself is unusual: a decommissioned federal uranium-enrichment plant in Pike County, about 50 miles south of Columbus, where SB Energy will run an on-site power plant under a fee structure tied to the 2025 U.S.-Japan trade agreement [1]. Only the first slice of the campus - roughly 800 megawatts of the eventual 10 gigawatts - is targeted to come online, in 2028 [1]. None of it is signed yet; both the Wall Street Journal's original report and follow-on coverage describe the talks as early-stage and subject to change [3][4].