Why the grid, not AI demand, pulled Microsoft out of Loughton
UK Power Networks told Nscale that adequate power for the 90MW Loughton connection may not arrive until the early-to-mid 2030s, versus the original roughly 2027 target [1]. That is the entire story mechanically: the site already had planning permission and a signed 90MW grid connection agreement in place, so the holdup sits strictly on the supply side, with the grid operator itself unable to commit a usable timeline [1].
This is not a Loughton-specific fluke. Ofgem data shows 315 data centers queued nationally for grid connections requesting a combined 73GW, more than the UK's roughly 45GW peak demand, with total cross-sector connection applications reaching 125GW, up from 41GW a year earlier [1][2]. Microsoft had agreed to take the entire 50MW-to-90MW scalable capacity and deploy roughly 23,040 Nvidia GB300 GPUs at the site [3]- a commitment that only made commercial sense if power actually arrived on a workable schedule, and a multi-year slip into the 2030s broke that assumption.